ARTICLE DETAILS
Time: 2022-01-19 17:33:15
Author: Guangzhou Juchen Stage Equipment Co., Ltd.
Click:
In recent years, the upsurge of theater construction has promoted the rapid development of stage machinery industry. Mechanized stage is not only equipped with a complete range of stage equipment, but also equipped with a variety of stage equipment. The construction of a professional performance stage project, if there is no perfect maintenance and maintenance plan, its use effect and safety factor can not be guaranteed.
I. Conditions for testing and acceptance:
1. The owner shall report the testing project and issue relevant invitation documents;
2. After receiving the invitation letter, the Tester shall make an appointment and arrange the time as agreed by both parties;
3. After determining the time, the tester shall prepare relevant testing equipment and key technical personnel;
4. Arrive at the scene and issue the test form of the testing party. After filling in the form, ask the owner (stage manager) to confirm and sign;
5. The stage manager shall report the test table and explain the reasons; Suggested mechanical equipment to be corrected; Assess the cost of the investment that needs to be rectified; Time required for rectification;
6. Environmental assessment; Cross-device influence; Evaluation of the impact of renovation on other stage equipment;
7. Effect evaluation after rectification; Safety risk assessment;
8. Rectify the warranty period of the theatre machinery and equipment and draw up long-term maintenance contracts; Determine the future responsibility for safe use; Make a plan for the safety insurance of stage equipment;